Thursday, October 2, 2014

Closed Week Update #3

On Wednesday, the project crew continued with the 10 inch main and nearly finished at the connection point near the 1st tee before darkness stopped work.  They are at it again today and working on cleaning up the trench, replacing sod, and moving machinery to work near the tunnel connections.

BHCC staff members sodded Teal Tees on #'s 14, 15, and 17 on Wednesday morning.  That only leaves two more tees, #'s 12 and 18 which will be finished up in the coming weeks.


Once the tees were finished, we moved on to the bunkers on #8.  The drain lines were exposed and tested and new contour lines drawn out.  Most of the excavation and grading will be done by hand so it's a very slow process even with 8 guys on the job.


When you're asking people to work this hard, day after day, you need to find some time to have a little fun.  For us, that means a friendly soccer game with the crew from United GLI Inc.  The game was very competitive, yet friendly, with more laughing than you'd expect.  Those who didn't play, parked carts in the shade to watch the action.  It's amazing that any of us have energy to work after playing hard for 30 minutes, but it seems to revive us and everybody grabs their shovels and heads back to the trenches.



More updates coming soon….